HS2 Notice- programme 2026

Published: 14 January 2026

Rugby Road

Duration

Full road closure in place,  on:
Monday 9 March to Sunday 22 March the road will reopen on the evening of 22 March

To complete the utility connections for BT and Seven Trent Water.

For further information please refer to the following link.

Leicester Lane (A445), Cubbington
To progress the construction of Leicester Lane Overbridge, BBV will be carrying out earthworks along the highway. There will be road closures and temporary lights at dates to be issued.

Monday 23 February to Friday 6 March 2026 a full road closure will be in place 24/7 and over the weekend.

 Offchurch Greenway Overbridge opening

The Offchurch Greenway Overbridge,  opened to the public on Saturday 11 October .

Works are progressing for the Cycle Bridge over the Fosse Way, which will connect the Offchurch Greenway to the Sustrans Cycle Route 41. For safety PRoW W192 will stay closed and be diverted through the new realigned Offchurch Greenway. There will be a clearly signposted diversion that will remain in place until 27 March 2026

Footpath diversion

Closure and diversion of PRoW W130b, to ensure users safety. The diversion will be in place until 31 December 2027. Pedestrians will still be able to safely navigate through the area by using the clearly signposted diversion.

For further information follow the link.

Location
B4113 Stoneleigh Road and Stareton Lane, Stoneleigh near Stoneleigh Park

Duration
B4113 Stoneleigh Road will be closed 24 hours a day, seven days a week from Monday 23 March now until Sunday 19 April 2026

 

 